What are the implications if the operation scrap is maintained in the routing and if it maintained in the BOM?
Page 1 of 1
What are the implications if the operation scrap is maintained in the routing and if it maintained in the BOM?
If the operation scrap is maintained only in the routing, the costing lot
size is reduced by this percentage.
If the operation scrap is maintained in the BOM, the planned input (not
the output quantity) is increased and any assembly scrap is reduced.
michael_fico- Posts : 163
Join date : 2012-03-23
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|
Mon Aug 20, 2012 4:37 pm by Admin
» Difference between Type and Like
Thu Jun 07, 2012 2:40 pm by Admin
» How to handle table control fields in Module Pool program?
Wed May 09, 2012 2:41 am by govind
» Three tables inner join in SAP
Thu May 03, 2012 4:47 pm by Uma_ABAP
» Creating table type in ABAP
Sat Apr 28, 2012 9:03 pm by Uma_ABAP
» Creating user defined types and structures in ABAP
Sat Apr 28, 2012 8:55 pm by Uma_ABAP
» Creating Dynamic Internal Table and Dynamic Field catalog in SAP-ABAP
Fri Apr 27, 2012 11:00 am by Admin
» Copy Custom PF-Status from Standard program to Custom Program in ALV
Thu Apr 26, 2012 9:52 pm by Uma_ABAP
» Calculate/find number of working days between two dates in SAP
Tue Apr 24, 2012 2:06 pm by Uma_ABAP