What is mixed costing in SAP? Give an example to explain.
Page 1 of 1
What is mixed costing in SAP? Give an example to explain.
Mixed costing is required when different processes are used to
manufacture the same material. Mixed costing is required when you have
different sources of supply for purchasing the material.
Let us take an example:-
There is a finished good Xylene which can be manufactured by 3
different processes.
The first process uses an old machine and labour. The processing time is
9 hrs to manufacture.
The second process uses a semi-automatic machine and labour. The
processing time is 7 hrs to manufacture.
The third process uses a fully automatic machine and the processing
time is 5 hrs.
Thus cost of manufacture for the 3 processes is different. By using Mixed
costing you can create a mixed price for the valuation of this finished
good.
michael_fico- Posts : 163
Join date : 2012-03-23
Similar topics
» What configuration needs to done for using Mixed costing?
» Explain the importance of asset classes. Give examples?
» What happens in an actual costing run?
» Explain the importance of the GR/IR clearing account.
» Explain the organizational assignment in the PA module?
» Explain the importance of asset classes. Give examples?
» What happens in an actual costing run?
» Explain the importance of the GR/IR clearing account.
» Explain the organizational assignment in the PA module?
Page 1 of 1
Permissions in this forum:
You cannot reply to topics in this forum
|
|
Mon Aug 20, 2012 4:37 pm by Admin
» Difference between Type and Like
Thu Jun 07, 2012 2:40 pm by Admin
» How to handle table control fields in Module Pool program?
Wed May 09, 2012 2:41 am by govind
» Three tables inner join in SAP
Thu May 03, 2012 4:47 pm by Uma_ABAP
» Creating table type in ABAP
Sat Apr 28, 2012 9:03 pm by Uma_ABAP
» Creating user defined types and structures in ABAP
Sat Apr 28, 2012 8:55 pm by Uma_ABAP
» Creating Dynamic Internal Table and Dynamic Field catalog in SAP-ABAP
Fri Apr 27, 2012 11:00 am by Admin
» Copy Custom PF-Status from Standard program to Custom Program in ALV
Thu Apr 26, 2012 9:52 pm by Uma_ABAP
» Calculate/find number of working days between two dates in SAP
Tue Apr 24, 2012 2:06 pm by Uma_ABAP